Batterie Annes weekly construction report
Location Details
Battery Annes
Diary Entry
5 June 1943 Batterie Annes weekly construction report
Naval Artillery Battalion 605, Batterie Annes, report for 30 May–5 June: ammunition bunker I was stripped of its shuttering. Excavation for the fire-control-post accommodation and crew accommodation and the levelling work continued. Battery personnel erected the washing, shower and decontamination barrack, improvised a firing range and strengthened the wire obstacles.
Source of Information
T-1022 Roll 2422, scans 0650–0651.