Ninety day generator fuel reserve required on the islands

Location Details

Atlantic Wall; islands (general provision)

Diary Entry

31 May 1943 Ninety day generator fuel reserve required on the islands

Subject: delivery and reserve holdings of emergency generating sets for the Atlantic Wall.

Extract: procurement of 2,400 emergency generating sets is intended for lighting command posts, batteries and resistance nests. So far, 159 sets have been delivered. At an annual average operating time of 4½ hours a day, each set requires 3 litres of petrol daily. The reserve per generating set should therefore be: on the islands, 90 days, equal to 270 litres.

Editorial note: The equipment totals concern the wider Atlantic Wall programme in this letter, not the Channel Islands alone. The island reserve clause is general; Jersey is not individually named.

Original source image 00309.jpg — T-312 Roll 1563. Ninety day generator fuel reserve required on the islands.