14 December 1942 Part 5
Summary
Island fortification programme shortfall
Location Details
Cotentin
Diary Entry
14 December 1942 Island fortification programme shortfall
Editorial note: The expanded translation says the numerical calculations are too degraded for reliable transcription; no missing figures have been reconstructed.
Corps had already warned that the allotted fortification programme could not be completed within the specified period. The report compares planned concrete volumes with actual progress in Cotentin and the Channel Islands, considers the resulting small number of works achievable, and stresses the adverse effect of labour shortages and removal of workers. It seeks measures to accelerate and support construction.
Source of Information
T-314 Roll 1603, expanded reading edition T314_R1603_English_Translation.docx. 14 December 1942 | Source PDF pages 761–762. Supplement to material retained from earlier editions.
_edited.png)